If I change a template, do existing projects update too?

Overview

One common question about template management is whether changes to a template affect existing projects.

Answer

No — updating or modifying a template will not change existing projects.

  • Existing projects remain as they are.
  • Only new projects created from the updated template will reflect the changes.

Example

  1. Create Template A and use it to build Project 1.
  2. Modify Template A by changing phases.
  3. Project 1 stays the same.
  4. Any new projects created from Template A will have the updated structure.

Best Practice

If you need existing projects to match a new workflow, adjust them manually or create a new project using the updated template.

Did this answer your question? Thanks for the feedback There was a problem submitting your feedback. Please try again later.

Still need help? Contact Us Contact Us